Standard Costing and Variance Analysis

Jump to Page

You are on page 1of 5

You're Reading a Free Preview
Page 4 is not shown in this preview.

Reward Your Curiosity

Everything you want to read.

Anytime. Anywhere. Any device.

No Commitment. Cancel anytime.

Although favorable fixed factory overhead volume variance are usually good news

Frequently (but not always), actual fixed factory overhead will show little variation from budget. This results because of the intrinsic nature of a fixed cost. For instance, rent is usually subject to a lease agreement that is relatively certain. Depreciation on factory equipment can be calculated in advance. The costs of insurance policies are negotiated and tied to a contract. Even though budget and actual numbers may differ little in the aggregate, the underlying fixed overhead variances are nevertheless worthy of close inspection.

An Illustration of Fixed Overhead Variances

Let's take one final look at Blue Rail. Assume that the company budgeted total fixed overhead at $72,000; only $70,000 was actually spent (seemingly a good outcome). Here our accounting objective will be to allocate the $70,000 actually spent between work in process and variance accounts. The temptation would be to book $72,000 into work in process and reflect a $2,000 offsetting favorable variance - but that would be the wrong approach!

Instead, the Work in Process account should reflect the standard fixed overhead cost for the output actually produced. We get to this calculated value by reconsidering the company's original assumptions about production. Assume that Blue Rail had planned on producing 4,000 rail systems during the month; remember that only 3,400 systems were actually produced - output was disappointing, perhaps due to the inexperienced labor pool. This means that the planned fixed overhead was $18 per rail ($72,000/4,000 = $18). Because three labor hours are needed per rail, the fixed overhead allocation rate is $6 per direct labor hour ($18/3). Use this new information to consider the following illustration for fixed factory overhead (remember from the earlier discussion that the standard labor hours for the actual output were 10,200):

Although favorable fixed factory overhead volume variance are usually good news

By reviewing this familiar looking illustration, you can see that $61,200 should be allocated to work in process. This reflects the standard cost allocation of fixed overhead that would be attributable to the production of 3,400 units (i.e., 10,200 hours should be used to produce 3,400 units). Notice that this differs from the budgeted amount of fixed overhead by $10,800, representing an unfavorable Fixed Overhead Volume Variance. In other words, since production did not rise to the anticipated level of 4,000 units, much of the fixed cost (that was in place to support 4,000 units of output) was "wasted" or "under-utilized." Thus, the measured volume variance is highly unfavorable. If more units had been produced than originally anticipated, the fixed overhead volume variance would be favorable (this would reflect total budgeted fixed overhead being spread over more units than originally anticipated). For Blue Rail, the volume variance is offset by the more easily understood favorable Fixed Overhead Spending Variance of $2,000; $70,000 was spent versus the budgeted $72,000. Together, the two variances combine to reveal a net $8,800 unfavorable Total Fixed Overhead Variance.

Journal Entry for Fixed Overhead Variances

The diagram below illustrates the flow of fixed costs into the Factory Overhead account, and on to Work in Process and the related variances.

Although favorable fixed factory overhead volume variance are usually good news

Following is a compound journal entry to apply fixed factory overhead to production and record the related variances:

8-31-XX

Work in Process Inventory

61,200

Fixed Overhead Volume Variance

10,800

Fixed OH Spending Variance

2,000

Factory Overhead

70,000

To increase work in process for the standard fixed overhead, and record the related volume and spending variances

Recapping Standards and Variances

The foregoing provided a painstakingly detailed account of the variances for Blue Rail. Before moving on, it is best to put the entire subject in perspective. The goal is to compare standard costs to actual costs. Blue Rail's work in process is recorded at the standard costs found in the Blue circles (hint - the work in process inventory of blue rails is recorded at the amounts found in blue circles), while actual costs are found in the red circles. These amounts are recapped in the table below:

Actual Cost to Account For

Standard

Cost Assigned to Work in

Process

Overall

Variances

Specific Variances

Direct Materials Price Variance Quantity Variance

$369,000

$340,000

$ (29,000)

$ (41,000) $ 12,000

Direct Labor Rate Variance Efficiency Variance

$175,000

$183,600

$ 8,600

$ 50 000 $ (41,400)

Variable Factory Overhead Spending Variance Efficiency Variance

$105,000

$102,000

$ (3,000)

$ 20,000 $ (23,000)

Fixed Factory Overhead Spending Variance Volume Variance

$ 70,000

$ 61,200

$ (8,800)

$ 2,000 $ (10,800)

AGGREGATE

$719,000

$686,800

$ (32,200)

You will notice that the standard cost of $686,800 corresponds to the amounts assigned to work in process inventory via the various journal entries, while the total variances of $32,200 were charged/ credited to specific variance accounts. By so doing, the full $719,000 actually spent is fully accounted for in the records of the Blue Rail.

Examining Variances

Not all variances need to be analyzed. One must consider the circumstances under which the variances resulted and the materiality of amounts involved. One should also understand that not all unfavorable variances are bad. For example, buying raw materials of superior quality (at higher than anticipated prices) may be offset by reduction in waste and spoilage. Likewise, favorable variances are not always good. Blue Rail's very favorable labor rate variance resulted from using inexperienced, less expensive labor. Was this the reason for the unfavorable outcomes in efficiency and volume? Perhaps! The challenge for a good manager is to take the variance information, examine the root causes, and take necessary corrective measures to fine tune business operations.

In closing this discussion of standards and variances, be mindful that care should be taken in examining variances. If the original standards are not accurate and fair, the resulting variance signals will themselves prove quite misleading.