Back to top Which of the following statements about the work breakdown structure WBS is correct?Option C is the correct answer. C. The WBS breaks the proejct deliverables down to the work package level, where cost and time estimates can be easily determined. The work package level is the lowest level in the work breakdown structure.
How does the WBS differ from the project network?While a WBS divides project deliverables into manageable pieces, a project network diagram takes those pieces and/or the tasks required to complete them and organizes them chronologically. In short, a work breakdown structure shows a whole and its parts while a project network diagram shows a sequence of events.
How are the WBS and project networks linked quizlet?How are W B S and project networks linked? The network uses the time estimates found in the work packages of the WBS to develop the network. Remember, the time estimates, budgets, and resources required for a work package in the WBS are set in time frames, but without dates.
Which of the following describes WBS?A Work Breakdown Structure (WBS) is a hierarchical outline of the tasks required to complete a project. The WBS “breaks down” the structure of a project into manageable deliverables. Each deliverable is assigned a task, or series of tasks that can be further broken down into subtasks to meet the needs of the project.
|